A4020 Uxbridge Road, Hayes
25 October — 03 November
Delays likely Traffic control (give & take)
Works location: A4020
Works description: Crossover Construction
Responsibility for works: Hillingdon London Borough Council
Current status: Planned work about to start
Meadvale Road, Ealing
09 October — 13 December
Delays likely Road closure
Works location: -
Works description: -
Responsibility for works: Thames Water
Current status: Planned work about to start

A406,A4005 Hanger Lane, Ealing

21 September — 01 November

Delays likely Road closure

Works location: A406,A4005

Works description: Hlg Resurfacing, Lining And Structures Lane Closures/ Slip Road Closures On Both N/B On Slip To Hlg And N/B Off Slip From Hlg Lane Closures/ Slip Road Closures On Both S/B On Slip To Hlg And S/B Off Slip From Hlg

Responsibility for works: Transport For London

Current status: Advanced planning

A406,A40 Western Avenue, Ealing

21 September — 01 November

Delays likely Road closure

Works location: A406,A40

Works description: Hlg Resurfacing, Lining And Structures Lane Closures/ Slip Road Closures On Both W/B On Slip To Hlg And W/B Off Slip From Hlg Lane Closures/ Slip Road Closures On Both E/B On Slip To Hlg And E/B Off Slip From Hlg

Responsibility for works: Transport For London

Current status: Advanced planning

A406 Hanger Lane Roundabout, Ealing

21 September — 01 November

Delays likely Road closure

Works location: A406

Works description: Hlg Resurfacing, Lining And Structures Multiple Inner And Outer Ring Lane Closures, Off Slip Closures And Road Closures

Responsibility for works: Transport For London

Current status: Advanced planning

Twyford Abbey Road, Park Royal

21 September — 01 November

Delays likely Road closure

Works location: -

Works description: -

Responsibility for works: Transport For London

Current status: Advanced planning

Western Avenue, Greenford
26 July - 06 May 2018
Delays likely Road closure
Responsibility for works: Transport For London
Current status: Planned work about to start

Gunnersbury Avenue (North Circular Road)

07 June — 16 November 2018

Delays likely Lane closure

Works location: -

Works description: -

Responsibility for works: Transport For London

Current status: Planned work about to start