Notification of Disruptive Ealing Broadway Crossrail Works

Forthcoming activity includes noisy night time piling this weekend

Participate

Sign up for our weekly Ealing newsletter

Comment on this story on the

Trackside work that Network Rail and their contractors are undertaking in the coming months, including Easter and the early May Bank Holidays, in the Ealing Broadway area is likely to cause some disruption to local residents. Much of this work must take place at night and at weekends when the trains are not running.

This weekend (1 - 2 April) noisy piling work has been rescheduled to take place. It will commence at 10pm on Saturday and is expected to conclude at 10am Sunday.

These works, which involve the installation of tubular steel pile foundations for overhead
line equipment, are part of the adjustment needed to the existing railway infrastructure
to enable the operation of the Elizabeth Line and Great Western Railway trains. In
order to achieve a safe working environment, sections of the track must be closed to
operational rail traffic whilst the works are carried out.

While the levels of disruption will vary, there will be periods of intense activity and the
work may be noisy. Network Rail say they will use a vibration method in the first instance, but will have to use the noisier hammer piling when ground conditions make the vibration method
ineffective. These works may cause disruption for neighbours in the vicinity.

Artists impression of Ealing Broadway
Artist's impression of Ealing Broadway Station

Mobile screens/barriers or enclosures will be placed around the breaking equipment and other noisy hand-held tools, where practical to do so.

There will also be an increase in the amount of work taking place over Easter and the early May Bank Holiday. They will be working 24 hours a day during these periods and therefore residents may suffer higher levels of disruption than normal.

During Easter and the early May Bank Holiday they will be extending platforms which includes some demolition work and installing mechanical, electrical, communication and security systems on platforms. Traffic may be congested at times on The Broadway and The Mall A4020 due to machinery and materials being delivered to site. At various times until December 2017 minor works such as deliveries, drainage, mechanical and electrical installations and site surveys will take place at Ealing Broadway station. All workers will receive daily briefs reminding them to be considerate to neighbours.

Monday 3 April to Thursday 13 April 2017

Monday to Friday daytime 08:00 – 18:00

Restoration works to College Court compound.

This work may be noisy at times due to the use of pneumatic drills breaking concrete obstructions. Delivery and removal of materials through Carmelita House and College Court will occur throughout this period, therefore reversing alarms and noisy vehicles may be heard.

Monday to Friday,21:00 – 06:00 &8:00 – 18:00

Various hours over Saturday and Sunday

* Excavation and installation of foundation bases, ducting and chambers on platforms

* Installing footbridge drainage and undertaking footbridge snagging

* Installation of mechanical, electrical and communication equipment

* Extending platforms, including foundations, resurfacing and drainage installation, and grading of the embankment

* Installation of capping beam to the sheet piled wall

* Conducting site surveys

* Delivering and removing materials.

This work may be noisy at times due to the use of pneumatic drills breaking concrete obstructions. A crane will be required to operate within the Carmelita House car park to deliver and remove materials for these platform works. Other vehicles will also be accessing Carmelita House car park for delivers, therefore reversing alarms may be heard.

Thursday 13 April to Tuesday 18 April 2017 – Easter weekend

Various hours between 22:00 Thursday and 06:00 Tuesday

Platform 3 – set-up of site working area; removal of part of the platform to prepare for platform extension; removal of platform ramp, construction of new platform foundations and blockwork wall construction.

Platform 4 – installation of foundation bases, ducting and chambers.

These activities will be noisy at times due to the use of pneumatic drills breaking platform surfaces. For these platform works a crane and concrete pump will be required to operate within the Carmelita House car park. Other vehicles will also be accessing Carmelita House car park for delivers, therefore reversing alarms may be heard. Platform 3 and 4 will be closed to the public during this period.

Tuesday 18 April to Friday 28 April 2017

Monday to Friday daytime 08:00 – 18:00

Restoration works to College Court compound.

This work may be noisy at times due to the use of pneumatic drills breaking concrete obstructions. Delivery and removal of materials through Carmelita House and College Court will occur throughout this period, therefore reversing alarms and noisy vehicles may be heard.

Monday to Friday,21:00 – 06:00 & 8:00 – 18:00

Various hours over Saturday and Sunday

* Excavation and installation of foundation bases, ducting and chambers on platforms

* Installing footbridge drainage and undertaking footbridge snagging

* Installation of mechanical, electrical and communication equipment

* Extending platforms, including foundations, resurfacing and drainage installation, and grading of the embankment

* Installation of capping beam to the sheet piled wall

* Conducting site surveys

* Delivering and removing materials.

This work may be noisy at times due to the use of pneumatic drills breaking concrete obstructions. A crane will be required to operate within the Carmelita House car park to deliver and remove materials for these platform works. Other vehicles will also be accessing Carmelita House car park for delivers, therefore reversing alarms may be heard.

For any queries, either before or while this work is taking place, call the dedicated 24-hour National Helpline on 03457 11 41 41 or email CRCrossrail@networkrail.co.uk.